The main switchboard (MSB) at Bairnsdale Wastewater Treatment Plant was manufactured approximately 30 years ago with limited automation and control functionality, nearing end of its design life. The switchboard, control system and related electrical installation required upgrade to comply with current standards.
As Electrical was appointed as the head contractor for this design and construct contract.
Ace Electrical was involved in the following scope of works:
All works had to be planned, designed and constructed in a manner that did not compromise the operational requirements of the plant.