Mernda Junction External Works

Location: Bridge Inn & Plenty Road, Mernda, Melbourne, VIC

Client: HACER

Date: February 2018 – February 2019

ACE were engaged by Hacer to complete the external infrastructure works at the new Mernda Junction shopping centre on Bridge Inn & Plenty Road, Mernda.

The scope of works consisted of new storm water drainage, installation of new HV conduits and substations, water reticulation system, public lighting, traffic signal intersection, concrete footpath, asphalt pavement construction and asphalt re-sheet.

 

Keilor Road Intersection Upgrade

Location: Niddrie,VIC

Client: VicRoads

Date:  May 2018 – Nov 2019

Ace Infrastructure completed the intersection upgrade works at Keilor Road / Newman Street and Keilor Road / Grange Road in Niddrie. The works under this contract included road widening, kerb and channel works, drainage, guard barrier works, fencing, public lighting, traffic signal, asphalt works, line marking as well as signage at 2 intersections.

There is estimated 7000 vehicles per day at this location.