Vic Rail Network Carpark Package

Location: Various, Melbourne, VIC

Client: Victorian Rail Track

Date: 2017 – 2018

This project included 5 carparks, 4 bike park stations, 11 bike hoop locations all spread from North Geelong all the way to Wodonga. All works were located at an operational station carparks being used for parking and railway travel by commuters.

 

WOODEND STATION

ACE delivered new car parking including pavements, drainage, footpath, lighting and CCTV, and soft landscaping at Woodend Station.

 

SEYMOUR STATION

Construction of a new railway station carpark including asphalt pavements, concrete footpaths, drainage, bike parking, CCTV and lighting.

 

MACEDON STATION

ACE constructed new car parking including pavements, drainage, footpath, lighting and CCTV, as well as soft landscaping.

 

WENDUREE STATION

ACE constructed new car parking including pavements, lighting and CCTV, drainage, footpath, as well as soft landscaping.

 

CLARKEFIELD STATION

A new railway station carpark was constructed including asphalt pavements, concrete footpaths, drainage,
CCTV and lighting.