Ace Infrastructure Bridge Update

Ace Contractors Group Pty Ltd > Blog > Ace Infrastructure Bridge Update

Taking shape outside Ballarat on the Yarrowee River is the new 2 lane, 3-span bridge with soil retaining walls, constructed by our highly experienced Ace Infrastructure team.

The 33 no. pre-stressed planks measured 11 & 14 metres long and weighed on average 11 tonne. They were lifted into place with a 250T mobile crane and crew. Scaffolding around the piers and abutment gave safe access to land the beams onto elastomeric bearing pads.

The new bridge, comprising 350m3 of concrete and 55T steel reinforcement, will be open in January 2021.

 